Home SeWa West Africa Ltd

POWER PLANT POWER EVACUATION

Project

Client

Country

Project-Period

A013: Alscon Grid Connection

Federal Ministry of Power

Nigeria

2008 - 2010

Purpose:

To evacuate surplus power from a captive power plant

Technical data:

ABB (Alstom) 560MW Single Cycle Gas Turbine captive power plant.

SeWa Services:

Analysis of the commercial risks of gas supply to the proposed power plant

  • Audit existing internal transmission system
  • Design power evacuation to national grid
  • Select Injection Substation
  • Survey route for connection power line

PDF Format