POWER PLANT EXTENSION

Project

Client

Country

Project-Period

Purpose:

Extend four Open Cycle Power Plants (Phase I) in the Niger Delta to Combined Cycle (Phase II)

Technical data:

Omotosho Power Plant Turbines
Open Cycle (Phase I) 8 x GE PG6581B (42.1MW)
Combined Cycle (Phase II) 4 x GE 9E (126.1MW) + 2 x ST (125MW)
Papalanto Power Plant Turbines
Open Cycle (Phase I) 8 x GE PG6581B (42.1MW)
Combined Cycle (Phase II) 4 x GE 9E (126.1MW) + 2 x ST (125MW)
Alaoji Power Plant Turbines
Open Cycle (Phase I) 3 x GE 9EA (126MW)
Combined Cycle (Phase II) 1 x GE 9EA (126MW) + 1 x ST (285MW)
Geregu Power Plant Turbines
Open Cycle (Phase I) 3 x Siemens V94.2 (153MW)
Combined Cycle (Phase II) 3 x Siemens V94.2 (153MW)
Combined Cycle (Phase III)

SeWa Services:

  • Review of EPC Technical and Financial Proposals
  • Negotiate total Phase II & III budgetary price
  • Recommendation of Phase II & III Project Cost
  • Represent Client as Owner's Engineer
  • Preparation of Contract Documents
  • Commissioning
  • Technical support during Defects Liability Period